Projected Timeline
Development Schedule
April 2024 - Enter Exclusive Negotiating Agreement (ENA) with City of Cupertino
July 2024 - Community Meeting #1
January 2025 - Community Meeting #2
Spring 2025 - Entitlement
Ongoing - Community Outreach
July 15 City Council Study Session
September City Council
October 2025 - Enter in Disposition and Development Agreement (DDA) with City of Cupertino
October 2025 - All financing obtained June 2026
November 2026 - Construction Start
January 2028 - Construction Completion
April 2028 - 100% Lease Up